UCLA DA 820.18: Construction Contracts |
---|
Date: |
October 08, 2008
|
From: | Administrative Vice Chancellor Sam J. Morabito |
To: | Associate Vice Chancellor, General Services Jack Powazek |
References: |
|
Supersedes: | UCLA DA 820.08 (Construction Contracts) to Assistant Vice Chancellor Powazek, dated 6/20/2005. |
- Execution of a contract for a project shall not cause the total cost of the Project (including site clearance, building construction, exterior utilities, site development, A&E fees, campus administration, surveys & tests, special items, construction contingency, and group 2 & 3 equipment) to exceed the approved capital improvement budget.
- Bid solicitations and contract awards shall comply with applicable State law and shall be subject to regulations and requirements specified in the University of California (UC) Facilities Manual and other requirements which may be established from time to time by the Office of the President, including the requirements stated in UC DAs: 1040 (Bonding Requirements for Construction Contracts), 2134 (Appointment of Executive Architects, etc.), 2136 (Approval of Project Design), 2157 (Transfers of Funds for Minor Capital Improvement Projects), 2158 (Amendments to CIP for Non-State Funded Minor Capital Improvement Projects) and 2159 (Amendments to CIP for Non-State Funded Major Capital Improvement Projects…Not to Exceed $5MM).
You are authorized to use the following modes of contracting as defined in Public Contract Code Section 10503, subject to requirements in the UC Facilities Manual: Complete plans and specifications (Lump Sum); Design-and-build (Design-Build); Construction manager (CM at Risk); and Cost-plus-fee.
Public Contract Code Section 10503(e) authorizes The Regents to solicit bids under such other contracting modes as The Regents determine to be in the best interest of the University, provided that such bids or proposals are compared on a uniform basis and that the award is made as determined by the published selection standards. You are hereby authorized to use the following additional contracting modes (pursuant to Standing Order 100.4(dd)), subject to the requirements in the UC Facilities Manual: Job order or delivery order; Time and materials; Energy retrofit and performance contracting and Unit pricing.
Subject to requirements in the UC Facilities Manual, you are also authorized:
- To consent to the withdrawal of a bid after bids are opened and the bidder claims a mistake, under the conditions specified in the UC Facilities Manual section on “Modification or Withdrawal of Bids after the Bid Deadline”;
- To negotiate and execute change orders to a construction contract, within appropriated funds; and
- To sign notices of completion in the name of the Corporation.
This delegation is being reissued due to an organization change and the reissuance of the parent UC DA which includes performance contracting and unit pricing as additional contracting modes, and references additional UC DAs that bid solicitations and contract awards must be compliant with. Any redelegation of this authority shall be in writing with copies to me and those listed below.
cc: | Chancellor Executive Vice Chancellor & Provost Vice Chancellor, Finance, Budget & Capital Programs Executive Vice President, Business Operations General Counsel & Vice President, Legal Affairs Universitywide Policy Coordinator Contracts Administrator, Capital Programs Manager, Administrative Policies & Delegations |